Brockman Mine ROM Pad, Western Australia



Brockman Mine ROM Pad, Western Australia
  • Client: Monadelphous
  • Contract: value $3m

Project description

As part of Rio Tinto’s Western Turner Brockman project, Monford completed concrete, reinforcement and earthworks for a run of mine (ROM) pad. As the works were integral to the mine infrastructure program, Monford worked to strict timeframes.

Scope of work

  • Supply and install formwork for slabs including scaffolding (140m2 )
  • Supply and install concrete (55m3 ), reinforcement (10t) for a barrier wall
  • Construct ventilation fan footings and install reinforcement and concrete
  • Install hold-down bolts
  • Excavate pits (320m3 ) and install concrete slabs for lighting poles (33m3 )
  • Backfill and compact fill materials in compliance with specifications (550m3 )
  • Install blinding concrete as per specifications
  • Supply and install isolation joints and wall joints
  • Install 12 bollards